Project title
|
Rehabilitation of tunnel No. 206 between station Trebešica and passing point Lutovo (km 367+480 to km 367+802)
|
Project description
|
The works will include washing and cleaning of the inner surface of the concrete substrate by removing the loose parts of the concrete; production and installation of perfo-anchors; production of reinforced concrete seals, repair of working joints and cracks, production and installation of steel centerings ; contact injection, construction of concrete lining by injection; production of a spray concrete layer, repair of the concrete lining with pumped concrete; waterproofing production , etc.
|
Funding source
|
Financing is provided by remaining EBRD loan funds
|
Contractor
|
GP Planum-AD Beograd
|
Supervision
|
IRD Engineering s.r.l, Italy with partners : SWS Engineering S.p.A, Italy; Građevinski nadzor i labaratorijska ispitivanja a.d. Crna Gora(Construction supervision and laboratory testing jsc. Montenegro); RAIng d.o.o. Podgorica, Montenegro
|
Contract work value
|
EUR 998.876,96 EUR NET VAT
|
Contract supervision value
|
EUR 92.100,00 excluding VAT (basic contract for supervision of rehabilitation works of 6 slopes and 5 concrete bridges has been expanded with the scope of work and supervision of rehabilitation works of the mentioned tunnel, in accordance with the procedures of the Bank).
|
Commencement of project implementation
|
4th quarter 2018.
|
Deadline of completion of works
|
4th quarter 2019.
|
Current status
|
Supervision has issued the commencement date instruction ( Commencement Date) 18.10.2018.
|