| Project title | Rehabilitation of tunnels number 187 (km 353+657,39 – km 353+895,93), tunnel number190 (km 354+831,93 – km 356+271,93) and tunnel number193 (km 357+235,96 – km 357+631,96) along the railway line Vrbnica – Bar in Montenegro (Contract number 7927-IFT-37232/8) |
|---|---|
| Project description | Works on tunnel rehabilitation include the following work items: T187: Reprofiling of tunnel lining 5-10 cm, contact injection, perfo anchor / IBO anchor installation, installation of spray concrete layer (shotcrete)of 3 -4 cm thickness, installation of waterproofing foil 20 mm thickness, installation of Q131 reinforcement mesh and installation of the II layer of spray concrete (shotcrete) thickness of 3-4 cm, as well as the repair of seals in the depth damage of the tunnel lining. At the exit part in the length of 21,40 m is installed sprayed waterproofing membrane Master Seal R 345, through which a layer of spray concrete (shotcrete) is installed. T 190 and T 193: Reprofiling of tunnel lining 5-10 cm, installation of micro-reinforced concrete with thickness of 5 cm, contact injection, installation of waterproofing foil thickness 8 mm, installation of reinforcement mesh Q188 and installation of spray concrete (shotcrete) thickness 5 cm, as well as rehabilitation of the seals on places of deep damage to the tunnel lining. |
| Funding source | EBRD - European Bank for Reconstruction and Development |
| Contractor | G.P. Planum, A.D. Beograd-Zemun |
| Supervision | Internal supervision formed by ŽICG |
| Contract work value | EUR 3,428,179.80 VAT excluded |
| Supervision contract value | Internal supervision of RIoM |
| Commencement of project implementation | I quarter 2016 |
| Deadline for work completion | IV quarter 2017 |
| Current status | All works are completed. Guarantee period is in progress. |